Parks Update

Chippawa Park

  • Excavation, drainage and concrete work to commence late October. Weather permitting, the majority of the landscape-related works are to be completed in fall 2021.
  • Play Equipment supply and installation anticipated February/March 2022 (weather permitting).
  • Rubber Surfacing and final landscape work April/May 2022.

Cooks Mills Park

  • Excavation, drainage and concrete work to commence early November. Weather permitting, the majority of the landscape-related works are to be completed in fall 2021.
  • Play Equipment supply and installation anticipated March/April 2022 (weather permitting).
  • Rubber Surfacing and final landscape works May / June 2022.

Elmwood Park

  • Excavation, drainage and concrete work to commence early November. Weather permitting, the majority of the landscape-related works are to be completed in fall 2021.
  • Play Equipment supply and installation anticipated March/April 2022 (weather permitting).
  • Rubber Surfacing and final landscape works May / June 2022.

Glenwood Park

  • Excavation, drainage and concrete work to commence mid to late November. Weather permitting, the majority of the landscape-related works are to be completed in fall 2021.
  • Play Equipment supply and installation anticipated April / May 2022 (weather permitting).
  • Rubber Surfacing and final landscape works May / June 2022.
Share Parks Update on Facebook Share Parks Update on Twitter Share Parks Update on Linkedin Email Parks Update link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>