Dain City Watermain Redundancy and Security of Water Supply

Subject to Council approval, the City of Welland is undertaking a watermain program along Canal Bank Street between Ontario Road and 320 m south of Highway 58A.

Construction

  • Installation of 65 m of watermain by open cut method from stub 320 m south of Hwy 58A to Canal Bank Street bridge
  • Installation of 155 m of insulated hung watermain on the Canal Bank bridge over the CPKC railway corridor
  • Installation of 152 m of watermain by trenchless technology under the Ministry of Ontario Highway 58A corridor
  • Installation of 1100 m of watermain by open cut method from Highway 58A to the stub south of Ontario Road
  • Trench restoration including granular and asphalt within the roadway
  • Hydrant installation


Traffic Disruptions

  • One-way traffic with flag persons through the construction zones when permissible (minor periods of road closures may be required throughout construction)
  • Open to two-way traffic nightly and on weekends/holidays when permissible


Impacts to Private Property

  • Topsoil and sod to be reinstated where disturbed due to construction activities
  • Driveway closures required for construction will be communicated in advance to affected property owners
  • Driveways that have been disturbed due to construction will be reinstated to match the existing material


Next Steps

  • Currently in construction, completion June 2025.