The proposed upgrades to Broadway include a new trunk sanitary sewer, watermain upgrades, storm drainage improvements and road rehabilitation.

Construction

  • New sanitary sewer on Broadway from Riverside Drive to Semley Avenue.
  • Improved storm drainage and extensions of the storm system.
  • New watermain between Kilgour Avenue and Semley Avenue.
  • New water and sanitary services installed to property line.
  • Full road reconstruction between Kilgour Avenue and Pietz Avenue, including new curb and gutters.
  • New asphalt and line painting from Riverside Drive to Semley Avenue.

Traffic Disruptions

Road Closure Update

  • Rolling block-by-block closures between Kilgour Avenue and St. George Street
    • Detours are posted for through access on Broadway and for access to the side streets.
  • Broadway will be closed at Kilgour Ave until May 26, 2023.
    • The posted detour route is Regional Road 54 (Prince Charles Drive) > Lincoln Street > Regional Road 27 (Riverside Drive)

Impacts to Private Property

  • Topsoil and sod to be reinstated where disturbed due to construction activities.
  • Driveway closures will be required during concrete works and while curing. Advance notice to be provided to affected properties.
  • Driveways that have been disturbed due to the construction will be reinstated to match existing material.