The City of Welland is undertaking a stormwater management facility cleaning and rehabilitation program to address three of the nine residential stormwater management facilities throughout the city.
Stormwater Management Facility Locations
- Michael Estates
- Towpath Village
- Coyle Creek
Pre-Construction Activities
- Fish and wildlife abatement, as per Ministry of Natural Resources and Forestry (MNRF) permits to be completed by October 15, 2025
- Wildlife exclusion fencing installed around each facility
Construction
- Dewatering of each stormwater facility to permit construction
- Removal, decanting, and disposal of accumulated sediment from each stormwater facility
- Complete grading and retrofit works for each stormwater facility
- Final landscaping restoration of each stormwater facility
Traffic Disruptions
- Limited traffic disruptions expected for equipment and material loading/delivery
- Two-way traffic will be maintained with proper traffic control measures during temporary limitations
Next Steps
- Construction activities are expected to begin in November 2025, with completion of all three stormwater facilities by July 2026