2024 Infrastructure Renewals - Maple Avenue and Bald Street

Share 2024 Infrastructure Renewals - Maple Avenue and Bald Street on Facebook Share 2024 Infrastructure Renewals - Maple Avenue and Bald Street on Twitter Share 2024 Infrastructure Renewals - Maple Avenue and Bald Street on Linkedin Email 2024 Infrastructure Renewals - Maple Avenue and Bald Street link

Welcome to the project page for the 2024 Infrastructure Renewals on Maple Avenue and Bald Street! This page is intended to provide residents, homeowners, business owners, and visitors with an overview of the reconstruction work, additional resources, and the opportunity to connect with the project team.

Scope of Work

This project includes the full reconstruction of Maple Avenue and Bald Street from Denistoun Street Frazer Street and the following work:

  • replacement of the water and sanitary sewers, including laterals/services to property with new cleanouts and curb boxes at the property line;
  • new road granular base;
  • base and top asphalt;
  • curbs and sidewalks;
  • drainage and intersection improvements

Traffic Disruptions

Lane closures will be required during the installation of the underground utilities. Block-by-block closures may be required at times to facilitate the installations, but local access will be maintained. Notifications for driveway closures to be provided to affected properties by the Contractor in advance of closing.

Water Shutdowns

If there are unforeseen emergency water shutdowns, every effort will be made to notify you; however, notification may not always be possible. If you experience brown or discoloured water, please allow the water to run until clear. Should the water remain discoloured after continuous flow for greater than 20 minutes, please contact the City's water department at 905-735-1700 ext. 3000.

Community Engagement

  • Public Information Centre (PIC):
    • A Public Information Centre was held on October 2, 2024. Presentation boards and long plots of the project area are now available for viewing on this webpage.

Welcome to the project page for the 2024 Infrastructure Renewals on Maple Avenue and Bald Street! This page is intended to provide residents, homeowners, business owners, and visitors with an overview of the reconstruction work, additional resources, and the opportunity to connect with the project team.

Scope of Work

This project includes the full reconstruction of Maple Avenue and Bald Street from Denistoun Street Frazer Street and the following work:

  • replacement of the water and sanitary sewers, including laterals/services to property with new cleanouts and curb boxes at the property line;
  • new road granular base;
  • base and top asphalt;
  • curbs and sidewalks;
  • drainage and intersection improvements

Traffic Disruptions

Lane closures will be required during the installation of the underground utilities. Block-by-block closures may be required at times to facilitate the installations, but local access will be maintained. Notifications for driveway closures to be provided to affected properties by the Contractor in advance of closing.

Water Shutdowns

If there are unforeseen emergency water shutdowns, every effort will be made to notify you; however, notification may not always be possible. If you experience brown or discoloured water, please allow the water to run until clear. Should the water remain discoloured after continuous flow for greater than 20 minutes, please contact the City's water department at 905-735-1700 ext. 3000.

Community Engagement

  • Public Information Centre (PIC):
    • A Public Information Centre was held on October 2, 2024. Presentation boards and long plots of the project area are now available for viewing on this webpage.
Share Project Location on Facebook Share Project Location on Twitter Share Project Location on Linkedin Email Project Location link

Project Location

about 2 months

Page published: 08 Oct 2024, 09:47 AM