The City of Welland is undertaking a road reconstruction program along Martha Court, Surrey Place, Laughlin Place, and Sauer Avenue. The proposed upgrades will include: a new asphalt surface, curb replacement, and sidewalk replacement.
Construction Limits
- Martha Court - Leonard Ave to Donna Marie Dr.
- Surrey Place - Bridlewood Dr. to East Limit
- Laughlin Place - Linwood Dr. to West Limit
- Sauer Avenue - Southworth St. to Bradley Av
Construction
- New granular road base and asphalt surface
- Catch basin repair and replacement including road sub-drain
- New curb and gutter replacement
- Rehabilitation and replacement of sidewalks
- Watermain replacement on Sauer Avenue
Traffic Disruptions
- One-way traffic with flag persons through the construction zones when permissible (minor periods of road closures may be required throughout construction)
- Open to two-way traffic nightly and on weekends/holidays when permissible
Impacts to Private Property
- Topsoil and sod to be reinstated where disturbed due to construction activities
- Driveway closures required for construction will be communicated in advance to affected property owners
- Driveways that have been disturbed due to construction will be reinstated to match the existing material
Next Steps
Construction start - September 2024
Share 2024 Road Reconstruction - Part 1 on Facebook
Share 2024 Road Reconstruction - Part 1 on Twitter
Share 2024 Road Reconstruction - Part 1 on Linkedin
Email 2024 Road Reconstruction - Part 1 link
2024 Road Reconstruction - Part 1
Page last updated: 09 Sep 2024, 12:55 PM